The Story of An Crubh

1 – Background  

2 – Initial funding and planning

3 – Architects

4 – Further funding

5 – Tender – there were a total of [  ] bids all of which exceeded the funding available so there followed a process of detailed negotiations between our professional advisors and the preferred bidder to reduce the projected cost combined with frantic efforts by CDI to secure additional funding.

6 – Construction – following the tendering process and subsequent negotiations with the successful bidder and additional funding from the Coastal Communities Fund construction began on the [   ] January 2016. The first sod was dug by [      ] and the site was then handed over to Compass.

7 – Completion – the building was finally handed over to CDI on the [23rd December] 2016 – a mere [  ] months after construction began.

8 – Opening